
Whether government agencies refuse to issue the required approvals to allow the project to proceed, or the process simply takes an exceptionally long time, there is almost always entitlement risk.
The entitlement process can take anywhere from 3 to 12 months, or sometimes longer.
Part of the reason entitlement takes so long is that city planners have different interpretations of local rules. You likely run into different attitudes and alignments between staff, planning commission, and city council. This can complicate the matter and delay a project’s launch.
At the same time, most development projects will go through several different aspects of the entitlement process, and some may also be required to go through multiple public hearings for approval.
Efforts to capitalize on dwindling land supply
Pressure is also on cities to capitalize on the dwindling availability of land, so they are making approvals increasingly harder and more costly to obtain.
The reality is, the price of a piece of land has three components: (1) the value of the physical fixtures, (2) the price of the land, and (3) the value of the things you can legally do with the land.
The value of the right to build can rise or fall with demand, just as the value of land can rise or fall with demand. So, as land supplies dwindle because of increased demand, the value of entitlements also increases.
The results…
Strained feasibility
- We’re seeing continued challenges in making projects feasible as land prices and construction costs continue to rise and the entitlement process remains challenging. Developers need to ensure proper and thorough due diligence before starting new projects to help minimize lengthy timelines and potential cost overruns.
Entitled property values soaring
At the end of the day, the entitlement process takes experience, patience and the right team with the right attitude to successfully sail through political issues, bureaucracy, and never-ending meetings and negotiations.